Chemical construction project approval procedures

There are more N procedures to do. Go to the government department window to get the project approval flow sheet and related cards. The processing of each document is N proof and approval.
overall:
Feasibility Study Report, Board of Directors Constitution, EIA Approval, Red Line Drawing, Preliminary Design and Approval, Energy Audit, Fire Approval, Construction Permit, Water, Electricity, and Earthquake Audit. Wait.
In general, companies need to set up a certification team.
Project approval process
1. Project application report and feasibility study report (12 days---Design Institute)
2. Revision of Board Resolutions, Articles of Association and Articles of Association (5 days - including mailing time)
3. Development and Reform Commission --------- Processing Letters for Preliminary Work (5 days)
[Business license (original copy 3 copies) + board resolution (1 original + 2 copies) + project application report (3 copies)]
4. EIA (60 days)
5. An evaluation (45 days)
6. Guardian Reviews (45 days)
7. State Land Bureau Pre-trial Review (14 days)
8. Development and Reform Commission --------- approved (15 days)
[Evaluation of Environmental Impact Assessment (3) + Approval of Safety Assessment (3 copies) + Approval of Weiwei Approval (3 copies) + Pre-review opinion of Land and Resources Bureau + Copy of planning site selection report (3 copies) + Copy of business license (3 copies) + Resolutions of the Board of Directors (1 original + 2 copies) + Copy of the latest audit report (3 copies) + Project application report (3 copies) + Bank credit certification (3 copies) + Work letter for preliminary work (3 copies)]
9. Foreign Economic Relations Bureau ---------Approved the change of approval certificate (10 days)
[Original original certificate original copy + application + power of attorney ("Authorized XX for ... business scope change matters...") + board resolution + statute + statute amendment case + original Foreign Economic Relations Agency approval + EIA + security appraisal + original business license original copy Piece + Latest Capital Verification Report + Latest Audit Report + Tax Certificate + Bank Credit Proof + Original National Land Certificate + Land Prequalification Comments + Feasibility Study Report + NDRC Approval Approvals (2 Plus 1)
10. Trade and Industry Bureau ---------Change of business license (3 days)
[Copy of Approval Certificate 1 Original + Original Copy of Original Business License + Application for Registration of Change in Foreign Investment Enterprise + Application + Board Resolutions + Regulations + Constitutional Amendment + EIA + Security Review] (1 original copy, 1 copy)
11. Development and Reform Commission ---------Confirmation of Foreign Investment Projects Entrusted by the State for Development (2 months)
[Provincial Development and Reform Commission approval copy (3 copies) + project application report (2 copies) + business license copy (3 copies) + import equipment list, domestic equipment list (12 copies) + tax registration certificate (copy 3 copies) + Approval Certificate (3 copies)
Prior to the approval of the National Development and Reform Commission, projects with more than 3,000 tons of standard coal will be subject to energy review.

Stainless Steel Bread Basket

Bread Basket,stainless wire basket,stainless wire bread basket,Metal Wire Bread Basket,steel bread basket,etc. we offered that you can trust. Welcome to do business with us.

Kichen Rack is made of high quality 304 stainless steel, This kind of material steel luxury, never rust, resist corruption, easily clean, safe, healthy and durable. Prevent rust or chemicals from contaminating food and damaging health

Stainless Steel Wire Bread Basket,Metal Wire Bread Basket,Creative Bread Basket,Versatile Bread Basket

Shenzhen Lanejoy Technology Co.,LTD , https://www.grill-mesh.com