·Indoor and outdoor cement concrete structure, mortar wall structure wall, ground;

· Waterproofing of the bathroom and bathroom, kitchen, floor, balcony, pool floor and wall;

·Used for smearing treatment before laying stone, tile, wooden floor, wallpaper and plasterboard to prevent moisture and salt pollution.

Base surface (substrate) treatment:

·The substrate must be firm, flat, clean, free of dust, greasy, wax, mold release agents, and other debris;

·There are pores, cracks and unequal defects on the base surface. It must be repaired and smoothed with cement mortar in advance. The expansion joint is recommended to be affixed with plastic strips. The joints must be coated with a layer of non-woven fabric. The nozzle filling is recommended to use Leibangshi nozzle grouting. filling;

· The yin and yang corners should be smeared into a circular arc (or V shape);

· Ensure that the base surface is fully wet, but no clear water;

• Newly poured concrete surfaces (including plastering surfaces) should be allowed to dry completely before application.

Instructions:

· Stirring: first pour the liquid into the container, then slowly add the powder, and stir for 3-5 minutes until a uniform slurry without powder and particles is formed; (preferably using a stirrer)

· Brushing: brush directly on the base surface with a brush or roller brush, the force is evenly used, can not be missed brush; generally need to brush 2 times (depending on the use requirements), each brush thickness does not exceed 1mm; before Once it is slightly dry, apply it again (just not sticky, usually 1-2 hours apart), vertical cross-over brushing, the total thickness of the brush is generally 1-2mm; if the coating has been cured, brushing The other layer is first moistened with water.

· Maintenance: After 24 hours of construction, it is recommended to cover the coating with a damp cloth cover or spray water.

·Inspection (closed water test): Please make sure that the waterproof construction is qualified after the waterproof layer is dry (at least 24 hours in summer and at least 48 hours in winter) for 48 hours. Lightweight walls must be tested for water spray.